Windsor Meadows & The Highlands Tentative Schedule
8/31-7am-4pm Mill Wildflower(up to Cornflower) and Cornflower
9/1-7am-4pm Mill Violet, Wildflower(up to Thistle), Sundew, Blue Bell
9/2-7am-4pm Finish Milling Thistle and Wildflower, Start Paving Cornflower Dr and Violet.
9/3-7am-4pm Pave Sundew, Blue Bell, Thistle, start Cornflower.
9/4-7am-4pm Pave the rest of Wildflower. Mill Meyer Ct and Rose Ct
9/8 7am-4pm Pave Meyer Ct and Rose CT
Road Improvement Projects
Other Capital Projects
8/31-7am-4pm Mill Wildflower(up to Cornflower) and Cornflower
9/1-7am-4pm Mill Violet, Wildflower(up to Thistle), Sundew, Blue Bell
9/2-7am-4pm Finish Milling Thistle and Wildflower, Start Paving Cornflower Dr and Violet.
9/3-7am-4pm Pave Sundew, Blue Bell, Thistle, start Cornflower.
9/4-7am-4pm Pave the rest of Wildflower. Mill Meyer Ct and Rose Ct
9/8 7am-4pm Pave Meyer Ct and Rose CT
Road Improvement Projects
| Project | Project Scope | Project Status | Estimated Start | Estimated Completion | Contractor |
| Phase II - Improvements to Meadowbrook Road | Milling, Paving, ADA Improvements | Final Inspection | -- | Substantially Complete | Earle Asphalt Co. |
| Roadway Improvements to Windsor Meadows | Milling, Paving, ADA Improvements | Pre-Construction | On or about 8/10/26 | 9/4/26 | MECO Inc. |
| Roadway Improvements to Sharon Mews & Hibiscus Ln | Milling, Paving, ADA Improvements | Pre-Construction | On or about 7/30/26 | Substantially Complete | R.T. Barrett |
| Roadway Improvements to The Highlands | Milling, Paving, ADA Improvements | Pre-Construction | On or about 8/17/26 | 9/8/26 | MECO Inc. |
| Roadway Improvements to Beechwood Dr & Hutchinson Rd | Milling, Paving, Signage, Striping, ADA Improvements | Bidding | TBD | Fall 2026 | TBD |
| Roadway Improvements to Pond Road | Milling, Paving, Signage, Striping, ADA Improvements | Delayed | Spring 2027 | Spring 2027 | TBD |
| Hankins Road Reconstruction and Safety Improvements | Reconstruction and Road Widening, Guiderail, Drainage Improvements | Design & Permitting | TBD | TBD | TBD |
Other Capital Projects
| Project | Project Scope | Project | Estimated Start | Estimated Completion | Contractor |
| Miry Run Recreation Area Trails Phase II | Paved Trails, Spur Trails | Grand Opening 5/28/26 | -- | -- | ANAR Construction |
| Miry Run Recreation Area Trails Phase III | Trails, connection to Washington Greene | Concept Design | TBD | TBD | TBD |
| Route 130 Pump Station | Replacement of Existing Sanitary Sewer Pump Station | Design & Permitting | TBD | TBD | TBD |
| Meadowbrook Road Pump Station | Replacement of Existing Sanitary Sewer Pump Station | Design & Permitting | TBD | TBD | TBD |